Free PMP Exam Sample Question

The following PMP® exam sample question is taken from The Free PMP Exam Simulator at http://free.pm-exam-simulator.com – The answer is at the very bottom:

——————————

Which of the following may be considered as the outputs of performing Quality Assurance?

A) Requested changes, recommended corrective actions, organizational process assets, project management plan.

B) Requested changes, requested preventive actions, Quality metrics

C) Quality management plan, Quality metrics, Quality baseline

D) Quality control measurements, recommended preventive actions

——————————

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try The PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

The Correct Answer is A.

Original post

Leave a Comment

Leave a comment

Leave a Reply